Mathis Ferry Trail

Description

Phase 1 of the Mathis Ferry Trail is proposed from the Scanlonville Praise House Trail at 5th Avenue to the Eagle Street crossing. This 5,800 ft segment is proposed along the north side of Mathis Ferry Road and is proposed to be concrete path that is 10ft to 12ft in width. Staff is pursuing Charleston County Greenbelt funds for Spring of 2023. Any letters of support for the project can be sent to the project manager James Aton at jaton@tompsc.com.

Schedule

  • Design Complete:  May 2024
  • Begin Construction:  TBD
  • Complete Construction:  TBD

Public Meeting

January 17, 2023

5:00 – 7:00 pm

 

Town Hall

100 Ann Edwards Lane

Mount Pleasant, SC 29464


Resources

mf_ion_after_v2eagle_st_after 

Project Manager

 James Aton

Jaton@tompsc.com

(843) 856-3080