Description
The project proposes to include pedestrian and bicycle accommodations along the length of Hale Road.
Status
Upon funding of a selected proposed segment project development typically takes approximately 3 months for Assessment and Survey, 6 months to prepare Preliminary Plans, 9 months for Final Plan preparation, and 12 months to start construction. Construction duration varies greatly depending on the complexity of the design.
- Assessment and Survey: In Progress
- Preliminary Plans: October 2023
- Final Plans: December 2023
- Begin Construction: TBD
Resources
Contact
Gary Ponder, Project Manager