MOUNT PLEASANT, S.C. (November 17, 2022) - The contractor is planning to start paving operations within the Fox Pond neighborhood beginning on Saturday, November 19, 2022. This operation will impact Fox Pond drive, and Poaug Lane at Fox Pond and Edwards Street. The speed humps on Edwards Street will be removed and replaced at a later date. The first phase will be the asphalt milling. Asphalt milling is the removal and leveling of the existing asphalt. This will result in the roadway being grooved to prepare for the application of new asphalt. This operation is expected to take one (1) day.
Once the milling is complete the roadway will be paved by the contractor. This operation is expected to take one (1) day.
All vehicles and any other obstructions must be removed from the roadway.